Price of California High-Speed Train Construction Increases $2.8B in Central Valley Alone

The estimated cost of building 119 miles of bullet train track in the Central Valley has jumped to $10.6 billion, an increase of $2.8 billion from the current budget and up from about $6 billion originally.

Construction workers at a viaduct being built to extend over State Route 99 and North and Cedar Avenues in Fresno County in this undated photo. (Credit: Marcus Yam / Los Angeles Times)

Construction workers at a viaduct being built to extend over State Route 99 and North and Cedar Avenues in Fresno County in this undated photo. (Credit: Marcus Yam / Los Angeles Times)

The new calculation takes into account a number of extremely costly problems encountered by the state rail agency. It raises difficult questions about how the state will complete the massive effort, the largest national infrastructure project, with the existing funding sources.

The new estimate was presented Tuesday by Roy Hill, who leads the main consulting firm on the project, WSP (formerly Parson Brinckerhoff). Hill said the cost increases were mainly driven by problems including higher costs for land acquisition, issues in relocated utility systems, the need for safety barriers where the bullet trains would operate near freight lines and demands by stakeholders for mitigation of myriad issues.

“The worst case scenario has happened,” Hill said bluntly.