L.A.’s $2B Metro Rail Line From Mid-City to South Bay Will Miss Its 2019 Deadline

A tunnel-boring machine breaks through at the site of Leimert Park Stationin this undated photo. (Credit: Irfan Khan / Los Angeles Times)

A tunnel-boring machine breaks through at the site of Leimert Park Stationin this undated photo. (Credit: Irfan Khan / Los Angeles Times)

A $2-billion light-rail line that will add a key north-south connection to Los Angeles County’s growing transit network is facing several construction problems and will not open next year, the Metropolitan Transportation Authority said.

Tunneling and track construction along the 8.5-mile Crenshaw Line through South Los Angeles has gone quickly, officials said, but crews have fallen behind schedule on electrical work, the connection to the Green Line, and improvements to sidewalks and gas lines in areas where the train will run at street level.

The accumulation of issues means the Crenshaw Line will not be ready for safety testing until December 2019, officials said. That will push the opening date back by about six months, to the late spring or early summer of 2020.

“We are committed to trying to expedite and compress our schedule as much as possible,” Metro spokeswoman Pauletta Tonilas said.

Read the full story on LATimes.com.